Get the news you want the way you want it: click the RSS button in the right corner to add this feed to your RSS reader, or click here to subscribe to this content. By subscribing, you’ll find this news on your Member Account page, and the latest articles will be emailed to you in your customized IndyBar E-Bulletin e-newsletter.

Criminal Justice News


Posted on: Jan 11, 2021

Progress continues on the city's new Community Justice Center, located in the Twin Aire neighborhood of Indianapolis. Work began on the campus in 2018 and completion is expected in 2022. 

There are 12 levels in the courts: Level 00/Ground through 11. Currently, the courts design builder is topping out drywall on levels 5 through 9, framing levels 10 and 11, installing stairs and working on elevators. Wilhelm has nearly completed backfilling the courtyard and installing utility distribution piping between the central utility plant and the courts building. 

The Assessment + Intervention Center opened on the community justice campus in December 2020. Read more here.